Business
Registration Certificate no longer
statutorily required with bid
P.L. 2009, c.315
(A-557/S2366): Relaxes
the requirements for Business Registration
Certificate submission with bids; permits
submission prior to award of contracts if
not submitted with bid.
Effective for bids received and
contracts awarded after January 18, 2010.
This law removed
the requirement of the Local Public
Contracts Law (N.J.S.A. 40A:11-23.2) that
required a bid to be rejected if the bidder
failed to include a business registration
certificate (“BRC”) with the bid, even
though it may have been the otherwise lowest
responsible bid.
The law now allows the BRC to be
filed anytime prior to award of the contract
and the bidder had to have obtained the BRC
prior to receipt of bids.
This permits the BRC to be required
with a bid, or submitted subsequently.
If a BRC is required in a bid, but
not submitted with the bid, it will most
likely be considered an immaterial defect;
curable by being filed prior to award of the
contract as long as the bidder had a BRC at
the time of the bid.
Price
adjustment permitted on contracts for
asphalt, cement and fuel
P.L. 2009, c.187
(A-436/S-2833): Permits
price adjustments in local public contracts
for asphalt cement and fuel.
Effective with contracts executed
after May 1, 2010.
In today’s economy, the price of
petroleum-based products can have a
significant impact on construction contracts
that involve large amounts of asphalt and
those that use large amounts of gas or
diesel fuel.
Uncertainty in petroleum price
fluctuations adds price risk to construction
bid calculations.
That uncertainty imposes additional
risk on bidders.
This new law follows procedures
historically used by the State Department of
Transportation (“DoT”) to allow for
increases and decreases in asphalt and fuel
prices over the course of large construction
contracts.
See
2007
NJDOT Specifications – Division 150
Contract Requirements, Section 160.01
through 160.03.
The law requires that
paving contracts involving more than 1,000
tons of hot mix asphalt include a contract
provision that allows for price adjustments
in the cost of asphalt.
Fuel price adjustments are based on
DoT standards for the type of construction
equipment and the work done by different
equipment.
For fuel price adjustments, at least
500 gallons of fuel based on the DoT
equipment standards are required for a price
adjustment, and then, only in those months
when the price fluctuated more than five
percent.
DoT maintains a web site
of index rates for asphalt and fuel that are
adjusted monthly.
The law provides that when the
quantity or equipment use thresholds are
reached, fuel price adjustments are made,
using the change in index rate from the time
of bidding to when the work was performed.
The change is treated as a “pay
item” in construction contracts.
This practice is not new to most
engineers that prepare bid specifications.
The law provides price risk
protection to bidders, allowing better bids
using “sharper pencils,” reduces the
risk of change orders that may be intended
to cover price increases, and allows the
contracting unit to take advantage of
reductions in pricing over the life of
a contract.
· DISCLAIMER
These
materials
are intended to provide general information
about the subject matter and are presented
with the understanding that neither
these materials nor the authors have, nor
intend to, render any legal or other
professional service or opinions. Anyone
dealing with a specific legal matter should
research any and all matters described
generally herein and should not act upon
this information without seeking
professional counsel. Please
do not
send us confidential information until you
speak with one of our attorneys and get
authorization to send that information.
|