| The time and resources in
estimating the bid price, the lost business opportunity,
the lost profit, etc… but that is all it should cost,
it does not cost the contractor his bid bond if
the mistake is an honest one and it is properly brought
to the public body’s attention.
There are three reported cases
that deal with a contractor’s ability to withdraw its
bid due to the contractor’s mistake. These cases
stand for the premise that if a contractor makes an
honest mistake in its bid and that contractor brings the
mistake to the public body’s attention before the
public body changes it’s position based on the
contractor’s bid, the contractor should be
permitted to withdraw his bid without penalty.
The court developed a four prong
test to determine whether the contractor should be
permitted to withdraw its bid without penalty:
( 1 )
the mistake must be of so great a consequence that to
enforce the contract as actually made would
be unconscionable;
( 2 )
the matter as to which the mistake was made must relate
to the material feature of the contract;
( 3 )
the mistake must have occurred notwithstanding the
exercise of reasonable care by the party making
the mistake;
( 4 )
it must be able to get relief by way of rescission
without serious prejudice to the other party,
except for loss of his bargain.
Conduit
& Foundation Corp. v. Atlantic City 2
N.J.Super. 433, 440 (Ch.Div. 1949)
Whenever I argued these cases in
court, I was usually arguing the law in front of a Judge
in order to get my client’s bid bond returned.
Some public bodies attempt to impose a “penalty”
against the withdrawing bidder because the bidder made a
mistake. The “penalty” was written into the
bid specifications and attempted to make the withdrawing
contractor liable for the difference that the public
body had to pay between the withdrawing contractor’s
bid and the next lowest bidder’s bid. The
contractor making the honest mistake should not lose its
bid bond or be penalized.
State laws and sometimes federal
laws define the value of bid bonds on public projects.
It should be noted that if the project is federally
funded, the amount of the bid bond can be greater.
In any event, the contractor’s liability should be
limited by the amount of the bid bond.
As the Supreme Court noted in
the Meadowbrook Carting case, a contractor could make a
calculated decision to withdraw his or her bid and
forfeit his bid bond if his bid was mis-estimated (not a
mistake but a judgment error). So how does the
public body distinguish between a bidder who wants to
withdraw his bid because he made a judgment error (such
withdrawal is NOT permitted) and a bidder that has made
an honest mistake? The answer is that the Court
will apply the four prong test described above. The
McElwee Group, LLC v. Atlantic County Utilities
Authority, 2009 WL 5062349 (App.Div.)
"Who
is the Owner?"
When the client asks me, after
explaining the bidding scenario, whether or not he/she
has a successful bid protest, my first question is
always "who is the owner?" While it
often seems like an irrelevant question, the identity of
the owner dictates which laws will be followed when
analyzing a defect in a bid.
This is particularly true in a
recently decided case, T.N. Ward, Inc. v. South
Jersey Transportation Authority, and Hunter Roberts
Construction Group, LLC, Docket No. A-3900-09T4.
In this case, the second low bidder complained that the
low bidder listed two subcontractors under one category
(for example two subcontractors were listed under the
structural steel category), without specifying the scope
of work each would perform. Under local public
contracts law ("LPCL" – the law applying to
municipalities, not the State), if the bidder lists two
subcontractors for a trade, the bidder must submit with
its bid a certificate which “shall set forth the scope
of work, goods and services for which the subcontractor
has submitted a price quote and which the bidder has
agreed to award to each subcontractor should the bidder
be awarded the contract.” N.J.S.A.
40A:11-16b.
Therefore, under the LCPL, if
the names of two bidders were submitted under the
structural steel and ornamental ironwork category, the
bid would be defective if it were not accompanied by a
certification describing the scope of work to be
performed by each such subcontractor in accordance with
a price quote from each such subcontractor. However, the
owner of the project in the case was that State of New
Jersey, not a municipality or township.
Accordingly, LCPL was not
applicable; but, State Bidding Law was. The Court
noted: "The Legislature has not seen fit to include
a similar provision the State Bidding Law (the ability
to list two subcontractors is not included in projects
owned by the State). That law lists the same five
categories for which separate plans may be included in
the specifications N.J.S.A. 52:32-2a.”
The court stated that had this been a project bid under
LPCL, the low bidder's bid would have been defective.
However, since the owner was that respective State, and
the applicable law of that State was different, the low
bidder's bid was not defective. The moral of the
story is to know "who is the owner”, follow the
appropriate laws and, as always, follow the instructions
on the bid forms. |