 |
Using the law without a Lawyer-practical guide to using
the Prompt
Payment
Law
Tough economic times call for different
strategies. My
father was born before the great depression.
He started an advertising business that he
later sold to McMillan Publishing.
If he wanted a letter typed, he typed it
himself, if he needed a letter mailed, he typed the
envelope and mailed it himself, if he needed to make a
sale, he made the call himself.
|
Take
Advantage of the Statute by Exercising your Rights
The
Prompt Payment Law (“PPL”) was passed in 2006 and
is applicable to contracts executed after September 1,
2006.
See Shore
Mechanical Contractors, Inc. v. Osborne Construction,
2008 WL 4107985.
It allows contractors to build their case for
payment during the project.
The PPL requires Owners and Contractors to pay
in a timely manner.
Under the PPL, if a certified payment is not
timely paid interest and attorneys fees accrue.
Now I know I was writing about recovering money
without the assistance of an attorney, but the loom of
attorneys fees is always an ominous additional burden.
I
have found that the best way to avoid litigation is to
show your opposition that you have the law on your
side.
This is the reason that building your case
while the contract is ongoing is invaluable.
You have the right to know where your payment
is and why you are not being paid.
The contractor should
no longer be subject to months of silence after
the submission of a payment application or the payment
application approval simply “not making it on last
meeting’s agenda.”
The statute requires payment “unless the
owner provides, before the end of the 20-day period, a
written statement of the amount withheld and the
reason for withholding payment.”
The subcontractor must be paid
within 10 calendar days of receipt of each periodic
payment.
Time is money, each week that an application
for payment sits unanswered is another week of
uncertainty for the business.
The statute requires the owner to establish a
record of the reason for non payment.
This will promote quicker settlements of
payment dispute and refinement of issues between the
parties.
The
contractor, on the other hand must exercise his
rights.
If more than 20 days since the submission of
your pencil copy has elapsed, question the party to
whom you have made your submission; put your question
in writing, this will require an answer in writing.
Since the law requires “a written statement
of...the reason for withholding payment,” you should
receive the same.
Upon receipt of the answer you will have an
issue you can work on, upon resolution of the issue
you should be paid.
If not, at least you will have a record; a
position in writing, which you can later dispute.
The
Prompt Payment Law is a tool for the contractor to use
to protect himself.
Like any tool it will only work for you if you
use it.
If the contractor keeps records and makes
requests in writing, he is better equipped to battle
for his due.
Keep meticulous records and let the other side
know you have done so, you may be able to avoid going
to court to recover the money that is due to you.
If you must go to court to recover payment that
is due on a contract that was entered after September
1, 2006, it would certainly be nice to be able to
collect interest, reasonable costs and attorneys fees
as provided by the Law.
|
|
· DISCLAIMER
These
materials
are intended to provide general information about the
subject matter and are presented
with the understanding that neither these
materials nor the authors have, nor intend to, render
any legal or other professional service or opinions.
Anyone dealing with a specific legal matter should
research any and all matters described generally
herein and should not act upon this information
without seeking professional
counsel. Please
do not send us
confidential information until you speak with one of
our attorneys and get authorization to send that
information.
|